Slips

All 590 low-level slips (Tiers 0 and 1) identified as caused by the event, have been remediated.

Consultants are currently completing designs for the 211 larger slips (Tiers 2 and 3) located on the following high priority roads: Taihape Road, Glengarry Road, Dartmoor Road, Kahuranaki Road, Kereru Road, Waimārama Road and Puketitiri Road. When the designs are completed, contractors will be engaged to begin physical works at these sites. 

The below tables will continue to be updated as information comes to hand.

Slip locations

Tier 2 slip locations across the Hastings District Council network

Tier 2 Slip Locations across the Hastings District

K1 - Kaweka (Puketitiri Road) Slips

There are two slip sites on Apley Road, these are located at RP: 2166 and RP: 2116 (pictured below). The design for both is expected to be completed in November 2024.

Apley Road RP 2.116 ATT315

 

There is 1 slip site on Corbin Road located at RP:0457 (pictured below). Design for this slip is pending.

Corbin Road RP 0457 ATT51

 

There are 6 slip locations on Crownthorpe Settlement Road (RP:2628, RP:2806 - pictured below, RP:4803, RP:5066, RP:8442, RP: 9698), all with design pending.

Crownthrope Settlement Road RP 2806 ATT108

 

There are 10 slip sites on Dartmoor Road (RP: 7690 - pictured below, RP: 7870, RP: 7950, RP: 10324, RP: 13575, RP: 13674, RP: 14384, RP: 16981, RP: 13670, RP: 10970) currently under construction.

Dartmoor Road (RP: 7690)

There are 3 slip sites on Flag Range Road with design pending. RP: 5489 pictured below

Flag Range Road RP 5489

There is 1 slip site on Glenross Road, with design pending. RP: 8807 (pictured below).

Glenross Road RP 8807 ATT199

There is 1 slip site on Hawkeston Road, with design pending. RP: 3560 pictured below.

site photo photos 20230404 021402

There are two slip sites on Hendley Road, with design pending. Slip at RP: 3580 picture below.

site photo photos 20230404 232534

 

There is 1 slip site on Makahu Road with design pending.

There is 1 slip site on Pukaututu Road with design pending.

There is 1 slip site on Potter Road with design pending. RP: 2543 pictured below.

Potter Road RP 2.543 to 2.692 ATT448

There are 4 slip sites on Price-Cockburn Road, all with design pending. RP: 2520 pictured below.

Price Cockburn Road RP: 2520

 

 

 

There are 16 slip sites on Puketitiri Road with planned construction in mid-2024. RP: 4463 pictured below.

Puketitiri Road RP 4463

 

There is 1 slip site on River Road with design pending.

River Road RP 8283

There is 1 slip site on Soldiers Settlement Road with design pending. RP: 3015 pictured below.

Soldiers Settlement Road RP 3015

There are 11 slip sites on Taihape Road. RP: 40275 pictured below.

Taihape Road RP 40275

 

There are 3 slip sites on Tareha Road, with design pending. RP: 8580 pictured below.

Tareha Road RP 8580

 

There are 17 slip sites on Waihau Road, with planned construction in mid-2024. RP:14766 pictured below. 

Waihau Road RP 14766

 

There is 1 slip site on Waitata Road, with design pending. RP: 0391 pictured below.

Waitata Road RP 0391

There are 9 slip sites on Whanawhana Road. RP:0826 pictured below.

Whanawhana Road RP 0826

There are 4 slip sites on Willowford Road. RP:2151 pictured below.

Willowford Road RP 2151

 

 

 

Tier 3 (major) slip locations across the Hastings District Council network

Tier 3 slip locations across the Hastings District

K2 - Kaweka (Taihape Road) Slips

Taihape Road RP42347 Slip

Description: This site had an underslip extending into the carriageway. The proposed solution includes an anchored retaining wall to prevent further erosion and support the reconstructed road. 

Impacts on road users: During construction one lane will be closed with traffic management set up for the other lane. Possible delays to be expected.

Estimated completion: August 2024

Taihape Road RP49999 Slip

Description: It was observed that the downslope from the carriageway had experienced a failure during the Cyclone Gabrielle event, extending into the carriageway with partial loss of one lane. Additionally, localised tension cracks were identified along the slope crest which show evidence of dislocation of an existing culvert.  A solution has been designed incorporating timber supports to stabilise and reinforce the site, allowing the road to be rebuilt.

Impacts on road users: During construction one lane will be closed with traffic management set up for the other lane. Minor delays are possible during the construction.

Estimated completion: July 2024

 

Taihape Road RP49750 SlipDescription: The failure at this site was a large underslip. We have completed the design of a timber retaining wall and this will be tendered in the new year with construction anticipated to start in autumn. 

Impact on road users: During construction one lane will be closed with traffic management set up for the other lane. Minor delays are possible during construction.

Estimated completion date: August 2024

Taihape Road RP49849 SlipDescription: This site had an underslip extending into the carriageway. The proposed solution includes an anchored retaining wall to prevent further erosion and support the reconstructed road. 

Impacts on road users: During construction one lane will be closed with traffic management set up for the other lane. Possible delays to be expected.

Estimated completion date: August 2024

Taihape Road RP40275 SlipDescription: It was observed that this site had a large under slip and undermining of the small timber wall. The design for this site has been completed and includes reinforcing the edge of the road with a timber retaining wall.   

Impacts on road users: During construction one lane will be closed with traffic management set up for the other lane. Minor delays are possible during construction.

Estimated completion: September 2024

Taihape Road RP45422 SlipDescription: This has an underslip meaning the side of the road has fallen away. We are finalizing the design of the permanent repair which will reinforce the slope to prevent further erosion and allow the road to be reconstructed.

Impacts on road users: During construction one lane will be closed with traffic management set up for the other lane. Minor delays are possible during construction.

Estimated completion date: September 2024

Taihape Road RP40141 SlipDescription: This site experienced at underslip of residual soil on the side of the gully. There is resulting saturation from the swale drain overflow. The detail design for this site is complete, and due for construction next year. The barrier footings will be stabilised and the stormwater will be directed along the outside corner away from the failure to avoid further damage in the future. 

Impact on road users: During construction one lane will be closed with traffic management set up for the other lane. Minor delays are possible during the construction.

Estimated completion: August 2024.

Taihape Road RP11230 Slip Taihape Road RP11302 Slip

Description: These two close locations experienced slips extending to the edge of the seal. The proposed design solution includes realigning the road slightly away from the slip through both of these adjacent slips. 

Impacts on road users: During construction one lane will be closed with traffic management set up for the other lane. Minor delays are possible during construction.

Estimated completion date: October 2024

Taihape Road RP40228 SlipDescription: Following the cyclone, the culvert at this site decoupled with fill embankment being washed away. The proposed design solution includes an anchored/cantilever UC/timber pole retaining wall with an integrated stormwater outlet, with the end of wall to bank tie-In is to be a gentle cut slope.

Impacts on road users: During construction one lane will be closed with traffic management set up for the other lane. Minor delays are possible during construction.

Estimated completion date: December 2024

Design expected to be completed 21/6/2024

Design expected to be completed 21/6/2024

T1 - Tutira (SH2) Slips

Design expected to be completed 13/3/2024

Design expected to be completed 22/3/2024

Design expected to be completed 22/3/2024

Design expected to be completed 22/3/2024

Design expected to be completed 5/10/2024

Design expected to be completed 5/10/2024

T2 - Tutira (SH5) Slips

Design expected to be completed 22/1/2024

Design expected to be completed 22/1/2024

P2 - Poukawa Slips 

Design expected to be completed 5/10/2024

Design expected to be completed 27/2/2024

M - Maraekakaho Slips

Design expected to be completed 22/12/2023

Design expected to be completed 22/12/2023

Design expected to be completed 2/2/2024

Loading...

Hastings District Council - Copyright © 2024 Hastings District Council

Disclaimers and Copyright
While every endeavour has been taken by the Hastings District Council to ensure that the information on this website is accurate and up to date, Hastings District Council shall not be liable for any loss suffered through the use, directly or indirectly, of information on this website. Information contained has been assembled in good faith. Some of the information available in this site is from the New Zealand Public domain and supplied by relevant government agencies. Hastings District Council cannot accept any liability for its accuracy or content. Portions of the information and material on this site, including data, pages, documents, online graphics and images are protected by copyright, unless specifically notified to the contrary. Externally sourced information or material is copyright to the respective provider.

© Hastings District Council - / +64 6 871 5000 / customerservice@hdc.govt.nz